Sump Pump inspections are being conducted in all active areas. Contact our outreach team if you are interested in learning more about our free sump pump program!


Cooke Glenmont

  • No activity in this area for the upcoming week

Schreyer Springs

  • Installation of new manholes and  basin excavation on Fairoaks
  • Downspouts and lateral lines are being installed in this area
  • Completed rain gardens will start getting winterized; straw matting will be added to prevent erosion and settlement.

Weisheimer Indian Springs Green Infrastructure

  • Crews are working on E Weisheimer Rd performing rain garden excavation
  • Water line work will begin on Village Dr
  • Completed rain gardens will start getting winterized; straw matting will be added to prevent erosion and settlement as well as the placement  of sod and continued landscape maintenance

Weisheimer Indian Springs Pervious Pavement

  • Cooke Way and Alley 2 are near completion! The permeable pavers are almost completely installed. Crews anticipate opening the road to local traffic during the week of 11/13
  • Dixon Ct. residents will have their driveway aprons poured with concrete on Monday 11/13. No access to driveways will be permitted but residents can park in front of their homes after work hours.

Blenheim Glencoe

  • There will be three crews in this area working; they will be on Fallis, Richards and Northridge Rd
  • Basin excavation for all Blenheim Glencoe sites will occur in 2018. Site prep and waterline/storm sewer work will occur this fall into early 2018.

Morse Dominion

 

  • Residents will receive a minimum 1-week notice prior to crews beginning any work.

 

  • No activity next week

Overbrook Chatham

 

  • Residents will receive a minimum 1-week notice prior to crews beginning any work.

 

  • No activity next week

 

*There will be a storm water improvement project starting up in Clintonville-This is not a Blueprint Columbus Project, but we would like everyone to be aware of the vehicles and equipment that will be in the area. Work for this project will begin 11/12/17 and they will start on Schreyer Pl. (Rosemont to Olentangy River)

*Columbia Gas will also be in the area conducting work. They will have crews working on Chatham Rd (High St to Sharon Ave) and on Beechwold Blvd (Sharon Ave to Indianola)

 

Please contact the Blueprint Outreach Team with any questions or concerns! Please note, if you do not receive a call back immediately it means we are collecting the necessary information to address your inquiry. We appreciate your patience!

Phone  614-645-1253  | Email blueprint@columbus.gov

For additional information please visit www.columbus.gov/Blueprint
Follow us on Facebook and Twitter @BlueprintCbus

 

2 Comments

  1. Could let me know what I need to do for the free sump pump program! 550 Northridge Rd. Columbus, Oh. 43214. 740-803-1848.

Leave a Reply

Your email address will not be published. Required fields are marked *